Viking Redningstjeneste AS
Project plan
Everything that has to happen to deliver Breif:: tasks, owners, deadlines, timeline and the budget behind it.
Viking 70th Anniversary Jubilee Weekend
Liwlig will deliver the Viking 70th Anniversary Jubilee Weekend at Oslo Airport Convention Center from 28 to 30 May 2027. The plan secures venue, accommodation, catering, transport, suppliers and production before building the programme, participant journey and continuous red line experience. Delivery concludes with reconciled accounts, participant feedback and an action report by 11 June 2027.
Kickoff and alignment
3 tasks · due 28 Aug 26Concept and creative
3 tasks · due 16 Oct 26Venue and logistics
4 tasks · due 20 Nov 26Suppliers and contracts
4 tasks · due 29 Jan 27Content and programme
4 tasks · due 30 Apr 27Communication and invitations
4 tasks · due 07 May 27Production and technical
3 tasks · due 14 May 27Onsite delivery
3 tasks · due 30 May 27Wrap up and evaluation
2 tasks · due 11 Jun 27Budget to deliver
By category
Risks
- Late approval of event date and commercial scopehigh
Approve the date, venue hold, budget ceiling and contracting authority by 28 August 2026.
- Airport hotel room inventory becomes constrainedhigh
Contract a protected room block with release dates and secure a secondary airport hotel.
- Programme contributions arrive too late for productionmedium
Issue fixed content templates, assign one client content owner and enforce review deadlines.
- Trade show suppliers provide inconsistent stand materialsmedium
Use a standard exhibitor manual, mandatory technical forms and one controlled stand package.
- Live vehicle displays create safety or access issueshigh
Approve vehicle movements with the venue, isolate display zones and use supervised loading windows.
- Nordic travel disruption affects attendancemedium
Use flexible travel terms, monitor arrivals and prepare remote contribution options for critical speakers.
- Food, accommodation or technical costs exceed allowancemedium
Track commitments weekly, protect the eight percent contingency and require written approval for scope changes.
- Historic material cannot be cleared for public uselow
Create an asset register with ownership, consent and usage status before gallery production.